Main INDEX
Monthly INDEX
PREV
NEXT
User name LeRose
Log entry time 16:02:36 on May 09, 2007
Entry number 201484
keyword=Shift Summary
Shift Summary 5/9/2007
John LeRose (SL)
Lingyan Zhu (TO)
At start of shift no beam
Accelerator planning to do beam studies starting at 08:30
10:55 Jack Segal makes opportunistic controlled access to check ARC HV
Jennifer Williams takes some air samples too.
Right dipole constant measured to be 18.561 minutes (no significant change)
Magnets shut down during ESR work then restored (quads were cycled)
14:23 We are out of controlled access
15:00 MCC says at least another hour (Folts and others go back into the Hall)
16:00 Waiting for beam (MCC says they're ready when the AES and RADCON
people leave the Hall)
No beam the whole shift!