• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name Holmstrom

    Log entry time 16:01:08 on May30,2007

    Entry number 203675

    keyword=Day Shift Summary

    8:00 Shift starts with data taking at 50 uA at Q2=24 fm-2


    9:06 We start moving the sectrometers to Q2=34 fm-2 configuration

    Left
    p0=1.895 GeV
    theta=33.2

    Right
    p0=0.5389 GeV
    theta=65.046

    9:08 MCC called they are going to start BCM calibration.


    11:00 BCM calibration postponed.

    12:35 Starting Production

    14:52 Beam away for 1 hour for hall B beam tune

    16:00 Shift end waiting for Hall B beam tune to end.

    Run Time Q2 I #(M)
    3881 7:58-8:28 24 50 1.25
    3882 8:28-9:06 24 50 1.25(start of run had bad beam)
    3883 Junk
    3884 12:34-13:37 34 50 1.25
    3885 Junk
    3886 13:56-14:52 34 50 1.03