User name Ramesh
Log entry time 00:08:45 on October27,2007
Entry number 209763
keyword=Shift Summary
Shift Crews: Kalyan, Eric, Ramesh
-----------------
17:23 Accelerator is having problems with the south linac. A vacuum
valve closes and they cannot open it. Don't know at the moment
wether it is an IOC to reboot or a manual opening to perform.
19:56 MCC ready to deliver beam. Alex needs about 15 minutes to leave the hall (he was in controlled access).
20:40 Ready to take beam. MCC is going to do Harp scan for us.
21:01 Harps work. Trying to do Bull's eye scan.
21:18 Bull's eye scan finished. This is the result:
Desired_(x,y)...Coda_run_no...BPMA..(x,y)......BPMB..(x,y)...Harp_run
-----------------------------------------------------------------
(0,0)...........20148.........(0.485,-0.38)...(0.009,-0.023)..lHA1H03B.10262007_21:22
(2,2)...........20149.........(2.041,2.160)...(1.998,2.009)..lHA1H03B.10262007_21:39
(2,-2)..........20150.........(1.935,-2.04)...(2.003,-2.008)..lHA1H03B.10262007_22:01
(-2,-2).........20151.........(-1.894,-2.347)...(-2.000,-2.004)..lHA1H03B.10262007_22:15
Rest of the time:
Taken optics target runs for NaI calibration.