Main INDEX
Monthly INDEX
PREV
NEXT
User name R. Michaels
Log entry time 13:38:05 on October29,2007
Entry number 210456
keyword=trig. cleanup, redundant scaler reads
There's been a concern about a too-high rate on L-arm. I don't
see anything wrong with the trigger, but I'd worry about double
pulsing at scaler, e.g. from unterminated cable. Scaler input looked
very clean for T3 and T4. Looked on 25 nsec scale up to 1 usec scale.
No extra features or reflections.
However ! The module which fed the scalers (a PS 757) did have a
reflection caused by the coax handshake cable. This cable was
properly terminated but there is evidently some flakiness on the
connector on the R-arm. What I did: I moved this cable to another
fanout module which is fed by the 1st fanout. The 1st fanout feeds
the scalers and trig. super. directly. This 2nd fanout should help
buffer the reflections. As for what happened during runs, one can
guess that the scope with 50 ohm termination changes the picture,
so may well have been reflections. FWIW, looks very clean now.
I did the same thing for T4: send a buffered copy to R-arm.
Now T1,T2,T3,T4 are all readout on chan 1-4 of the norm. scalers
on both HRS. I used Coax 1,2,3,5 for these resp. (coax 4 is busted).