At the morning MCC meeting we discussed the issues surrounding the energy
change this week.
The issue of when to perform the energy change arose after the Hall was
informed by the Cryo Group of the need to defrost the heat exchanger and
warm return line to the CHL. To do this the coolant to the Hall targets
needed to be shut off. This renders the targets out of use until coolant
to the cryostat can be returned. It is estimated to take approximately 2
days time to defrost the heat exchange equipment and warm return line to
an acceptable level. The hope is that allowing for this two day warm up
and defrosting will allow the Hall to keep the targets cold until they
are idled for the Thanksgiving Holiday in about two weeks time.
A pass change from 2-Pass to 4-Pass was scheduled for today, with the
energy change to 800 MeV/pass to follow on Wednesday. With the target
warmup this pass change was rendered unusable at this time. As a result
yesterday (11/05) we requested a shifting of the energy change by 2 days
from Wednesday to Friday. Hall C reluctantly agreed on Monday (11/05);
however, Hall B was opposed, as was MCC.
MCC was concerned, justifiably about slipping the schedule in this
manner. During this morning's 07:45 meeting MCC suggested moving the
energy change up one day to today (Tuesday 11/06) if the staff could be
coordinated to perform the energy change. Hall's B & C were agreeable to
this scheduling change. After some looking into the schedule, and
coordination among the halls, D. Skopik, and the MCC, the decision to
move the energy to today was decided upon. The energy change started at
10:00 today.
Thus, the ARC energy measurement, bull's-eye scan, and current
calibration originally set for today will NOT take place today. We will
have to reorganize these tasks for after the beam returns.
Tomorrow we will go to Restricted Access for the surveys of the
spectrometers and target harps. The target harps were moved about last
week to correct/understand why we were not seeing all three wires on harp
1H03B. Several people have asked to go into the hall to look at some
issues which have arisen (such as Cerenkov channel 10 HRS-L, moving gas
bottles in for the targets, etc.). After the survey of the spectrometers
is complete, they are to be moved to 120 degrees.
The following will need to be scheduled/rescheduled:
1) 3-Pass beam at 700 MeV/pass: On or about 12/15 (to compensate for
the loss of 4-Pass beam at 500 MeV/pass)
2) 2-Pass beam at 800 MeV/pass: Between 11/14 and 11/19. The plan is
to shift the 2-Pass Hall A running and Hall B 4-Pass running (where we
should have come up after the energy change tomorrow (11/07)) to the end
of the 800 MeV/pass running period just before the Thanksgiving holiday
break.
3) The other associated beam study activities,
a) ARC energy measurement
b) Current calibration
c) Bull's-Eye scan
and so on.