    User name Jack

    Log entry time 09:23:58 on March 04, 2008

    Entry number 228571

    keyword=Detector work yesterday

    Yesterday the detectors were installed in the Left Arm and the Detector Stack pulled back into the Shield House. Some gas connections and cabling still need to be done. The bottom S1 paddle still needs to be rotated. The present configuration is now: VDCs, S1, SC1, Gas Cerenkov(short), SC2, S2(not S2m), Carbon Doors, SC3, SC4, Pion Rejector.