    Log entry time 00:21:45 on June 6, 2008

    Entry number 241198

    keyword=Beam Time Accounting
    Hall A

    06/05/08 1600-2400
    Experiment #: E08-007
    Shift Leader: J. P. Chen
    Shift Workers: Z. Ye, I. Pomerantz

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.690.930.860.990.950.940.930.897.17
    Beam Available
    but Not in Use
    0.010.020.020.010.030.010.010.010.11
    Beam Not Available
    or Unacceptable
    0.300.050.120.000.020.050.070.100.72
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.001.001.001.001.008.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00
    Bbite0.000.000.000.000.000.000.000.000.00

    Comments: 16:00 production data taking

    Data Entry by: jpchen