    Log entry time 17:53:38 on August 18, 2008

    Entry number 242142

    keyword=Left HRS DAQ Status: Functional

    With help from Kalyan and Alexandre, the left HRS DAQ is now functional.

    We reconnected the cables for T3 and L1A that go from the trigger
    supervisor on the left HRS to the one on the BigBite weldment, though
    these cables are only temporarily connected. When the left detector
    stack is moved out for the RICH installation, these cables need to be
    disconnected. The ribbon cable that contains the address from the BigBite
    TS to the Left HRS TS was also reconnected.

    We verified that the ROCs were being gated by the L1A signal and have a
    rate of about 6-7 Hz.

    We are now beginning the cosmic checkout of S1, S2m and A1.

    A copy of this log entry has been emailed to: segal@jlab.org,rom@jlab.org,camsonne@jlab.org,kalyan@jlab.org