    User name V. Sulkosky

    Log entry time 19:41:25 on October 10, 2008

    Entry number 243642

    Followups:

    keyword=Left HRS Gas Cerenkov Recabled

    The HV and signal cables for the left HRS gas Cerenkov have been
    reconnected. I noticed that the foam around PMT # 8 on the left side
    of the detector was coming away from the PMT mount. The base for this
    PMT was also loose. All the other PMTs appear to be fine.

    The detector stack is now in the detector hut. However the A/C unit will
    be replaced on Monday and there is a chance the stack might have to come
    back out. By the end of Monday, we should be able to reconnect the HRS
    DAQ to the BigBite DAQ to resume cosmic checkout of the HRS and setup
    the coincidence time with BigBite.

    A copy of this log entry has been emailed to: bogdanw@jlab.org,ycwang@jlab.org