    User name V. Sulkosky

    Log entry time 22:30:27 on October 15, 2008

    Entry number 243713

    keyword=Left HRS DAQ Reconnected

    With Kalyan's help, I have reconnected the cables between the left HRS and BigBite weldment. The cables are now fastened to the left HRS detector stack. If the stack needs to come out, either Kalyan or I should be notified so we can take the cables back down.

    I verified that we are receiving the signals sent from the BigBite weldment. Kalyan is taking data with the BigBite configuration, so tomorrow morning, I will start testing the left HRS configuration.