User name R. Subedi
Log entry time 10:09:23 on January20,2009
Entry number 256907
keyword=Run Coordinator Report: Jan 19, 2009
Run Coordinator Report for Jan 19, 2009:
# Polarity status of the spectrometers: BigBite -ve (for e-), L-HRS +ve (for &pi+)
# &pi+Vertical mode with the half-wave-plate IN
Charge Accumulated Summary So Far
Half Wave Plate Charge Expected (C) Charge Accumulated (C) Comment
&pi- Vertical IN 3.5 0.86 -
&pi- Vertical OUT 3.5 4.04 Done
&pi-Transverse IN 3.5 0.62 -
&pi- Transverse OUT 3.5 4.38 Done
&pi+ Vertical IN 3.5 3.99 Currently here
&pi+ Vertical OUT 3.5 3.72 Done
&pi+ Transverse IN 3.5 4.5 Done
&pi+ Transverse OUT 3.5 3.66 Done
Overall Plans
1. Will stay at &pi+ Vertical mode until Thursday Morning.
2. Will do Moller measurement later today or tomorrow.
3. Will do positron runs on Thursday (Jan 22) Day/Swing and Swing/Owl(Friday) where
Day/Swing [starting 08:00]: BigBite +ve polarity and L-HRS +ve
Swing/Owl [starting 17:00]: BigBite +ve polarity and L-HRS -ve
4. Friday 08:00: BigBite will be back to -ve polarity, L-HRS stays at -ve polarity.
Activities
- Smooth production on polarized 3He at Vertical mode.
- Compton rate has been pretty good most of the time but goes worse sometimes in the Swing.
It will be taken care of during tomorrow's beam study time.
Beamtime Accounting:
ABU BANU BNA Comment
Owl 7.17 0.15 0.68
Day 7.22 0.50 0.29 DAQ crash
Swing 6.94 0.40 0.68