    User name gilman

    Log entry time 12:59:32 on February 9,2009

    Entry number 260020

    Followups:

    keyword=partial shift summary Feb 9 day


    At start of shift, N2 pressure scan:

    run pressure start end events comments
    1172 8 torr - 8:04 0.85 M
    1173 104 torr 8:10 8:20 0.68 M
    1174 207 torr 8:21 8:23 bad prescales
    1175 207 torr 8:25 8:35 0.77 M
    1176 304 torr 8:38 8:42 no 300 torr setting in plan - oops
    beam unstable - up and down - delay start of next run
    1177 398 torr 8:56 9:06 0.77 M
    1178 611 torr 9:09 9:19 0.65 M
    1179 810 torr 9:21 9:31 0.55 M

    9:32 ask MCC to set up for Moller

    13:00 Moller ongoing