User name riordan
Log entry time 20:07:44 on March 04, 2009
Entry number 264597
keyword=Summary for Mar 3 Swing - Mar 4 Day
Summary for Mar 3 swing - Mar 4 Day
Finished LHRS positron running last night. Charge accumulation is
near what was expected.
Performed Moller measurment Tuesday evening.
Switched back to negative polarity near start of day shift, but have
had only had about 1 hour of beam due to several magnet problems.
Beam in Use
Shift |
ABU |
BANU |
BNA |
2009/03/03 Swing | 4.09 |
2.36 | 1.15 |
2009/03/04 Owl | 5.09 |
1.72 | 1.19 |
2009/03/04 Day | 0.95 |
1.13 | 5.93 |
TOTAL | 10.13 |
5.21 | 8.27 |
Main events/issues:
- Mar 3
- Continued running with positron data taking.
- Moller for 3/3 was 80.3 +/- 2.0%, in agreement with Compton
- Mar 4
- Finished positive polarity running and switched back to negative
polarity.
- Problems with an ARC magnet prevents data taking from about
09:00 to 16:00.
Plans for the next few days:
- Continue 5-pass transverse production until pass change.
- Pass change will occur either late tomorrow afternoon or (more
likely) Friday depending on how work progresses in Hall C's magnet and
chicane reconfiguration.
- Will start 4-pass running with longitudinal polarization. Moller
will be done Friday night.
- 4-pass positron running will likely take place on Monday day when
techs are available.