Entry number 269632
keyword=Finally production running
After many problems we have started with the production running
on polarized He3 target with Transverse polarization (pol. is
36.1%) We set the prescales to LT3 = 7, LT4 = 15, RT1 = 7 RT2 = 40.
The first production run numbers are: #1647 and #20533.
Quick description of our problem:
1.) We had problems with the left arm coda, because the run numbers
were not increasing. They were stuck at (#1640). We called Brad for
help and he fixed the problem.
2.)Then similar problem appeared with the HRS-R coda. The run number
shown in coda window was #20528 while the HRS-R daemon was trying to
write into file #20525. We again called Brad for help. We had to reboot
the right arm TS0. After that things started to work.
3.) Then we had to do all the beam and T3 rate tests. They were all ok,
and finally we were able to start production data taking.
A copy of this log entry has been emailed to: brads, sirca, miham