    keyword=FADC VME crate modification

    The 2nd VME scaler unit is now cleared by a NIM signal at the same time of the FADC start. The 20 MHz clock still goes into channel 3 and the GSO trigger is now copied to channel 6 of both scalers. This occurred during Compton Run 16967