08:00 requested for controlled access to check the Q1;
08:00 Shift begins with controlled access to fix Q1.
10:05 Q1s are back to normal, requested for beam permit, and started short recovery procedure;
10:15 NMR 56%
10:17 Left dipole tripped (quench). Tried reset and turned it back on. Looks like it's coming back;
For why we are having cryo problem with Q1 and the dipole, see CLOG entry 1471881.
10:28 completed short recovery procedure.
10:28 started HAPPEX run 31440.
10:30 started production on the right arm; Left run 2899 had fluctuating dipole setting.
10:43 Left dipole is back, now taking data on both arms.
11:00 Left DAQ problem, fixed;
11:52 Beam HWP inserted;
12:02 started HAPPEX run 31441;
12:48 Beam away for injector optimization;
13:26 NMR 58%;
13:30 beam is back;
14:19 started HAPPEX run 31442;
14:44 Compton electron detector was inserted while we are doing a CODA reboot;
Production runs this shift:
HWP OUT:
Left:
2902, 5M
2903. 3M
Right:
21779, 1.4M
21781, 3.7M
21782, 2.2M
HWP IN:
Left:
2904, 2905, 2908-2911
Right:
21783, 21784, 21786-21789