• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT
    Make New Entry, Make Followup Entry

    User name miham

    Log entry time 21:31:32 on June 8,2009

    Entry number 279998

    keyword=Reference cell filled with N2



    I have removed Hydrogen from the target and put Nitrogen
    in. I made a mistake in the middle of the process and
    vented the cell while it was evacuated and let Air in.
    Because of that mistake I had to do the whole procedure twice.
    Here is a brief description of what I did:

    JOB | GAS | Left Gauge | Right Gauge
    ------------------------------------------------------
    Before | H2 | 1 (Ovfl.) | 133
    Ventilation | H2 | 749(50) | 000(-1)
    Evacuation | 0 | -009 | -015
    Filled | N2 | 866-889 | 020
    ------------------------------------------------------
    Ventilation#2| N2 | 749(50) | -001
    Evacuation | 0 | -009 | -015
    Vented #3 | Air | 701 | -002
    (By mistake) | | |
    Evacuated | 0 | -009 | -015
    Filled | N2 | 863-881 | 019
    Ventilation#4| N2 | 750 | -001
    Evacuated | 0 | -009 | -015
    Filled | N2 | 871-898 | 020
    -----------------------------------------------------
    After a while .... and with beam on
    -----------------------------------------------------
    | N2 | 881-907 | 021







    FIGURE 1

    FIGURE 2