User name H. Gao
Log entry time 17:14:10 on June12,2009
Entry number 280811
keyword=day shift summary
8:00 am, Start changing the momentum of Left and Right HRS to 3.0855 GeV/c
8:33 am NMR measurement. P=64%
8:33 Hall A goes to controlled access.
9:55 called MCC to go to beam permit
10:35 set left-arm to 3.35 GeV/c, right arm to 3.0855 GeV/c
10:45 Jack needs to go down the hall to reset the HV crates. Called for controlled access
12:05 Jack is done with controlled access. Called MCC for berm permit.
14:30 MM is about to put beam into the hall
~16:00 MCC started to put beam into the hall