User name Lindgren
Log entry time 16:03:46 on June14,2009
Entry number 281365
keyword=Shift Summary
8:00 June 14 day shift beginning
SL Richard Lindgren
TO Andrew Puckett
3rd Lamiaa El Fassi
Nitrogen calibration run in progress
8:09 Run 3587 HRS-L 22442 HRS-R nitrogen run ended
Back to production running
Transerse polarization 55.5%
Change target to 3He
8:17 Start HRS-R Run 22443 HRS-L Run 3588
High Voltage Crash due to beam
8:47 Start HRS-R 22444
One row of neutron detector votage still off
start again
8:52 Start 22445 HRS-R 3590 HRS-L
9:20 AM
HV bbps1:2001 and bbps1:2002 crashed due to wild beam excursion. This has happened 3 times now.
Call MCC to see if they can stop this.
9:30 Start 22446 HRS-R and 3591 HRS-L
9:35 End Compton Run. End of run failed. Reset configure, and download. Start again. OK
9:56 End Run 22446 and 3591
9;56 Start Run 22447 and 3592
10:25 End Run 22447 and 3592
10:26 Start Run 22448 and 3593
10:55 End Run 22448 and 3593
10:56 Start Run 22449 and 3594
11:24 End Run 22449 and 3594
11:26 End HAPPEX Run 31530 and start HAPPEX Run 31531
11:27 Start Run 22450 and 3595
11:56 End Run 22450 and 3595
11:57 Start Run 22451 and 3596
12:25 End Run 22451 and 3596
12:27 Start Run 22452 and 3597
12:58 End Run 22452 and 3597
12:59 Start Run 22453 and 3598
13:25 End Run 22453 and 3598
13:26 Start Run 22454 and 3599
13:56 End Run 22454 and 3599
13:57 Start Run 22455 and 3600
14:22 End Run 22455 and 3600
14:23 Start Run 22456 and 3601
14:50 End Run 22456 and 3601
14:50 Start Run 22457 and 3602
15:18 End Run 22457 and 3602
15:30 End Run 31531 HAPPEX Start Run 31532 HAPPEX
15:21 Start Run 22458 and 3603
15:51 End Run 22458 and 3603
15:52 Start Run 22459 and 3604
16:00 End day shift