    User name R. Michaels

    Log entry time 16:29:25 on September 4,2009

    Entry number 288027

    keyword=Dummy hole alum. tgt. part I

    Note added about previous runs: ps8=20, so T8 was
    about 10% of the total rate. Didn't mean to do that.

    Next steps:

    Put in the dummy hole alum. target.
    VDCs not on yet.

    Check rates and such

    L-HRS T1 = 700 Hz
    L-HRS T2 = 980 Hz
    R-HRS T1 = 165 * 4 = 660 Hz (correcting by x4)
    R-HRS T2 = 280 * 4 = 1120 Hz (ditto)

    Run 24658 / 4467 without VDCs

    Alum hole seen.
    It's a little off in Y. Let's see, it would want to
    move another roughly +0.3 mm to be centered, but we
    will leave it.
    Note: The beam is hitting the frame in Y slightly.

    See fig 1 and 2.

    Next step is to turn on VDCs.




    FIGURE 1

    FIGURE 2