    Log entry time 19:53:45 on September 14, 2009

    Entry number 289550

    keyword=Hall A Access Activities for September 15, 2009

    Hall A Access Activities for September 15, 2009


    The beam will be taken away for the C-50 commissioning at 7:00am. The hall will go into controlled access after that. Please contact me if you want to do work in the hall and haven't already let me know.


    In the Hall


    Other Planned Activities

    1. We have requested a Mott measurement from the accelerator folks before and after the spot move.
    2. We have also asked that the power supplies for the Moeller quads be checked out, since their current readings seemed to be fluctuating when we were at the MCC this morning.