    keyword=Beam Time Accounting
    Hall A

    09/22/09 0000-0800
    Experiment #: E05-109
    Shift Leader: G.M. Urciuoli
    Shift Workers: TO A. Giusa, 3rd F. Meddi

    00000100020003000400050006000700Total Time
    Acceptable Beam
    in Use
    0.820.780.870.830.670.050.000.234.25
    Beam Available
    but Not in Use
    0.040.040.040.040.140.670.670.572.22
    Beam Not Available
    or Unacceptable
    0.150.170.080.120.180.280.330.201.52
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.001.000.330.331.006.67
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.670.670.001.33
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.670.670.001.33
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments:

    Data Entry by: G. M. Urciuoli