0800 | 0900 | 1000 | 1100 | 1200 | 1300 | 1400 | 1500 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0.42 | 0.00 | 0.83 | 0.33 | 0.75 | 0.75 | 0.83 | 0.75 | 4.66 |
Beam Available but Not in Use | 0.00 | 0.21 | 0.08 | 0.33 | 0.13 | 0.08 | 0.08 | 0.18 | 1.10 |
Beam Not Available or Unacceptable | 0.58 | 0.78 | 0.08 | 0.32 | 0.13 | 0.17 | 0.08 | 0.07 | 2.22 |
Accelerator Con- figuration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Experiment Ready | 1.00 | 1.00 | 1.00 | 1.00 | 0.83 | 0.92 | 0.92 | 0.82 | 7.48 |
Planned Config- uration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.08 | 0.08 | 0.18 | 0.35 |
Unplanned Experiment Down | 0.00 | 0.00 | 0.00 | 0.00 | 0.17 | 0.00 | 0.00 | 0.00 | 0.17 |
Hall not ready reasons | |||||||||
Target | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Data Acq | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Other | 0.00 | 0.00 | 0.00 | 0.00 | 0.17 | 0.00 | 0.00 | 0.00 | 0.17 |
HRSL | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HRSR | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HALL_OFF | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Comments: Dustin McNulty changed BANU from 2.43 to 1.12
Data Entry by: Kowalski