Run Coordinator's Report for Saturday November 28 Day to Sunday
November 29 Owl
Summary
- 4 shifts in the next week need a volunteer. Please sign
up!
- On Day shift MCC did a brief tweak of some injector parameters which
improved the Compton rates considerably.
- A successful deadtime study was done during Day shift for about 3
hours.
- During Owl shift there were muliple magnet trips. Eventually the
RHRS Q1 went down and couldn't be reset. Ed made an access
today and tried increasing the lead flows but that didn't help. The
power supply is suspected and we will have to run with only the LHRS
until tomorrow.
- We achieved ~630 K good LD2 pairs for slug 10 in the last 24 hours,
some with the LHRS only.
Run Plan
- High current production running throughtout weekend.
- Today there will be Compton studies for about 3 hours at low
current, possibly combined with opportunistic Q2 measurement and
Moller.
Requests
- 4 shifts in the next week need a volunteer. Please sign
up!
- Shift Leaders: please write a detailed shift summary (including
runs taken and any
activities) and submit the BTA for each shift. Please log CODA reboots
in the halog and shift summary.
- 3rd person: Please make sure to start and stop the HRS DAQ
at the same time as the parity DAQ and to do the prompt analysis and the
HRS analyzer for every run.
- 3rd person: please keep a careful eye on the online data display.
Most problems can be caught quickly this way.
- Please make sure that the shift checklist is done once each shift.
Data taken
- Production charge taken in the 24 hours ending Sunday Owl: 3.3 C
- Total production charge taken in all, end of Sunday Owl: 43.3 C
Shift Summaries and BTA Reports