    User name Markowitz

    Log entry time 01:01:59 on June 27, 2010

    Entry number 328605

    keyword=LRSH set to 800 MeV/c for detector work

    The left HRS is at 0.800 GeV/c for the detector commissioning. Bogdan and Philip are in the hall, adjusting the width of the Cerenkov ADC gate from 120 ns to 60 ns.

    The sieve slits have been taken out.

    The optics multi-foil carbon target is in.