User name brads
Log entry time 11:16:41 on September 27, 2010
Entry number 332914
keyword=Experiment status update/summary
Mon Sep 27 11:14:56 EDT 2010
- See this link for a runplan outline
https://hallaweb.jlab.org/wiki/index.php/Start_up_run_plan
- MCC/Accelerator
- 'Hot checkout' of beamline magnets ONLY is deferred until Tuesday at
earliest
- PD will check with Ron Lauze as to whether this early partial
checkout is
worth the overhead
x delivery to Hall B should happen today
- note problem with CHL will shut things down tomorrow
x some issues with cryo levels in RF zones over the weekend are to be
investigated (CHL contamination problem?)
x Harps, PSS tested ready to go
x no "show stoppers" on MCC side other than cryo-related problems
- ESR
x warmed up over weekend, cleared (they hope) the ice, recooling today
- CHL has contamination
- 1--2 day down minimum, starting Tuesday morning
- not sure how/if this impacts ESR cooldown
- meeting on CHL issue at 1:30pm today
- Other Cryo-related issues:
* Note that cooling the LHRS magnets will need to be done with Hall open
- will take about a week to cool the magnets,
- my understanding is that we should be able to take some beam in the
evenings in parallel with this process, but we will have to work
with the
Techs on scheduling
* Note that cooling target will need to be done with Hall open
* Note that cooling Moller will need to be done with Hall open (just
guessing
on this one)
- Target (Meekins)
x spoke with Folts and Meekins
- leak not found yet, still investigating this morning
- in afternoon, Meekins will have to work on Qweak target...
- Arc Energy system (Arun)
- 9th dipole is functioning
- scanner HW and SW status unknown - emailed Arun requesting status update
- Lumis (Kalyan)
x mostly ready, but noisy
x is connected to RHRS scalers and injected using event 140 system
- data aren't exposed to the software yet (not sure what the problem is)
x lots of noise on system (ringing and 60Hz)
- adding RC filter !?
- Moller (Sasha, Jixie)
x ready to go, tested at 1kHz MPS --> HW and SW working
x tested system with LED pulser, in good shape
x magnet is already precooled using LN2, just waiting on ESR now
- should be able to cool in a day or so
- Note that cooling magnet will need to be done with Hall open (I
presume)
- Note that we will eventually need to do alignment through solenoid, must
bypass compton chicane for this
- could impact scheduling of beam quality tuning
- ie. do Moller alignment first, then steer and optimize through
Compton
chicane?
- Compton (Eric Fuchey)
x DAQ mostly ready
- missing 'prescaler' <-- Alex
- Megan Fried is the only person who really understands the DAQ software
- she is willing/able to come onsite for 1--2 weeks, but this needs to
be scheduled
x HW 'should' be OK, but is is not powered on yet
- Eric will work with others to test system and get back to me
- DAQ (Alex, others)
- 'Logic module' needs to be updated/fixed so that LHRS and Calorimeter
singles can be taken
- there is discussion about requiring all trigs but T5 to be disabled
for the
production configuration since the Calorim ADCs don't get gated on an
LHRS
single
- wasn't clear to me if the 'logic module' fix above solves this, or if
there really does need to be multiple CODA configurations to handle
singles triggers...
- was problem with 1875 TDC in LHRS as of Friday
- fixed, replace now?
- BPMs, BCMs, Raster status
- all 'should' be plugged in somewhere, but not fully verified on
software side
- BCM scalers are working
- need to verify BPMs plugged into ADCs (in both arms!)
- need to verify Raster signals plugged into ADCS (in both arms)
- Calorimeter (Alex)
x ARS unit(s) had firmware updated over weekend
- seems to have fixed a crash problem
- some readout/sync errors remain
- needs to be incorporated into complete DAQ (LHRS + Calorimeter) so it is
possible to take singles
- at the moment the Calorim ADCs only get a gate on a Calorim
trigger, any
other trigger will cause a readout problem
- LHRS (Isham, Julie)
- all detectors were working at one point, but haven't been tested for a
while
- can't take LHRS singles cosmics triggers in present configuration
- EDTM status unknown
- not clear if experiment cares about it
- [Segal] NOTE that the power supplies have seem major repairs and need
to be
recommissioned. This will take 2--3 day shifts _after_ the magnets
are cold.