Target leak has been fixed, we will be doing a hot checkout of the beamline (no beam, just magnet and instrumentation checks) starting at 6pm. We will return to Restricted Access when MCC is done (2--3 hours).
The CHL is recovering, and the ESR is continuing to cool. So far, so good. Assuming the accelerator comes back online during Wednesday DAY shift, there is a good chance we will lock up and take some beam during Wed SWING / Thurs OWL. The Hall will return to Restricted access during DAY shift Thursday. These plans are very preliminary though, so keep tuned.
The Hall A RC report with additional detail may be found here: https://hallaweb.jlab.org/wiki/images/a/aa/DVCS-HallA-meeting_28Sep2010.pdf