Log entry time 00:07:55 on February11,2011
Entry number 346336
keyword=Swing Shift Summary
16:00 Shift started. Target operation trainning was going on.
17:30 Target operation training finished. Jian-ping checked the Loop1
target temperature sensors and reset the alarm threshold for both loops. He found some problem about these sensors in Loop1. Check log entry 346309 for details.
20:30 Hall was closed for sweeping
20:45 Ramped up bigbite magnet to 518 A. Ramped up HRS magnets, set left arm momentum to 2034 and righ arm to 2190.
21:25 MCC called saying that the radcon can not sweep the spot behine
the left arm Q1 power supply box. There was a "High Voltage, Danger!" sign posted there which block the way. We need to take care of the post and redo a sweep by then.
21:50 Retuened to Restricted access
22:10 Alex cleared the sign and close the hall for sweeping
23:30 Finished sweeping the hall.
23:45 Asked MCC for beam.