    keyword=Swing shift summary

    16:00 Shift started. Hall is in restricted access
    17:20 Hall closed for sweeping
    18:10 Hall was in controlled acess, Alex, Brad, Vince, David, Zhihong, Aiden were working for various tasks
    21:10 Hall closed. Ask MCC to delieve beam.
    21:20 Cycled Left Q2 and Q3
    21:40 Ramp BB magnet current to 518A
    22:10 Called MC to check beam status, they said they have problems
    in tuning the beam at comptom quadrapole
    23:25 Right Dipole finally ramp up to set point
    23:27 MCC told that they are going to delieve tune beam