User name Holmstrom
Log entry time 16:02:02 on February24,2011
Entry number 348452
keyword=Day Shift Summary
8:00 Shift starts with a LHRS Q1 trip.
8:15 Q1 recovers, start data taking on D2 target.
9:00 Beam ends start of beam studies.
12:25 Change the right arm momentum on request to 0.585GeV/c.
16:00 Shift ends with Beam studies still ongoing.