    Log entry time 15:57:55 on February 13, 1999

    Entry number 14217

    keyword=Beam Time Accounting
    Hall A

    2/13/1999 0800-1600
    Experiment #: E95-001
    Shift Leader: P.Zolnierczuk
    Shift Workers: M.Jones, K.Sleifer, R.Suleiman

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    60 60 45 50 60 60 60 60 7.58333333333333
    Beam Available
    but Not in Use
    0 0 5 0 0 0 0 0 0.0833333333333333
    Beam Not Available
    or Unacceptable
    0 0 10 10 0 0 0 0 0.333333333333333
    Accelerator Con-
    figuration Chage
    0 0 0 0 0 0 0 0 0
    Experiment
    Ready
    60 60 55 60 60 60 60 60 7.91666666666667
    Planned Config-
    uration Change
    0 0 5 0 0 0 0 0 0.0833333333333333
    Unplanned
    Experiment Down
    0 0 0 0 0 0 0 00
    Hall not
    ready reasons
    Target 0 0 15 0 0 0 0 0 0.25
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 0 0 0 0 0
    Data Acq 0 0 0 0 0 0 0 0 0
    Other 0 0 0 0 0 0 0 0 0

    Comments: 08:00-10:45 smooth data taking (Q^2=0.4, th_targ=62.5 deg); 10:35-10:50 beam off, changin target field orientation; 10:50-16:00 smooth data taking (Q^2=0.4, th_targ=242.5 deg);

    Data Entry by: P.Zolnierczuk