0000 | 0100 | 0200 | 0300 | 0400 | 0500 | 0600 | 0700 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 1 | 1 | 45 | 1 | 1 | 45 | 36 | 57 | 7.05 |
Beam Available but Not in Use | 0 | 0 | 15 | 0 | 0 | 10 | 0 | 0 | 0.416666666666667 |
Beam Not Available or Unacceptable | 0 | 0 | 0 | 0 | 0 | 5 | 24 | 3 | 0.533333333333333 |
Accelerator Con- figuration Chage | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Experiment Ready | 1 | 1 | 45 | 1 | 1 | 50 | 1 | 1 | 7.58333333333333 |
Planned Config- uration Change | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Unplanned Experiment Down | 0 | 0 | 15 | 0 | 0 | 10 | 0 | 0 | 0.416666666666667 |
Hall not ready reasons | |||||||||
Target | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSe | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSh | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Data Ac | 0 | 0 | 15 | 0 | 0 | 0 | 0 | 0 | 0.25 |
Other | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Comments: main expt.. down: DAQ main machine down: RF trips
Data Entry by: Templon