1600 | 1700 | 1800 | 1900 | 2000 | 2100 | 2200 | 2300 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0 | 0 | 42 | 1 | 1 | 1 | 1 | 1 | 5.7 |
Beam Available but Not in Use | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Beam Not Available or Unacceptable | 1 | 1 | 18 | 0 | 0 | 0 | 0 | 0 | 2.3 |
Accelerator Con- figuration Chage | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Experiment Ready | 30 | 15 | 1 | 1 | 1 | 1 | 1 | 1 | 6.75 |
Planned Config- uration Change | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Unplanned Experiment Down | 30 | 45 | 0 | 0 | 0 | 0 | 0 | 0 | 1.25 |
Hall not ready reasons | |||||||||
Target | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSe | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSh | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Data Ac | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Other | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Comments: Time lost at start due to AC problem in hadron hut, accel. problems beam back just after 18:00
Data Entry by: ransome