Log entry time 00:10:06 on June27,2000
Entry number 44942
keyword=Swing shift summary
16:00 FPP chamber still has problems. Ask for access to check it
There was the gas flow problem. The E-Arm VDC efficiency was only 90%. Both the E and H-Arm VDC multihit distributrion were not good. Checked
the FPP TDC output, seemed no problem. Jack fixed the gas problem.
18:00 Changed target from LH2 to Carbon. Ask 5uA with raster off for Harp
scan and Moller measurement.
Eugene came to do the moller measurement.
20:28 Moller measurement is finished.
Joe started the ep measurement
Jack went down to the Hall to adjust the gas flow.
00:00 Joe is still doing the ep measurement. FPP straw efficiency is slowly getting
better.
_____________________________________________________________________
Codarun# Harp#
2548 945
Time Run Comment
20:03 2549 VDC and FPP chamber check
2550 test run
2551 test run
2552 test run
2553 test runs for VDC and FPP chesk.
_____________________________________________________________________