User name Rikki
Log entry time 00:01:55 on November10,2000
Entry number 51787
keyword=shift summary
16:00 Still waiting for beam.
16:45 MCC has informed us that a water main for one of their dipoles has broken and soaking a power supply in the arc. This means no beam for 4-8 hours.
20:25 Beam is coming back.
20:31 Beam back long enough to check raster (run #1183)
Run #1184-1186 JUNK
20:58 MCC is having trouble giving 50 uA without trips. Trying 45 uA.
21:03 Begin run #1187 at ~43 uA
21:13 End run #1187 (no beam last 2 min) - 94000 events
Trouble with one cavity tripping.
21:24 Begin run #1188
21:53 End run #1188 - 299 K events
BLM trips. MCC wants to send pulsed beam.
22:03 Begin run #1189
22:06 End run #1189 - 24 K events - FPP HV trip
22:25 Begin run #1190
23:24 End run #1190 - 600 K events - cavity tuning
23:27 Begin run #1191
continuing at end of shift