    Log entry time 16:03:22 on November 13, 2000

    Entry number 52018

    keyword=Beam Time Accounting
    Hall A

    11/13/2000 0800-1600
    Experiment #: e99007
    Shift Leader: gilman
    Shift Workers: Pentchev, Margaziotis

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    12 52 0 0 15 48 50 50 3.78333333333333
    Beam Available
    but Not in Use
    0 0 60 0 0 0 0 0 1
    Beam Not Available
    or Unacceptable
    48 8 0 60 45 12 10 10 3.21666666666667
    Accelerator Con-
    figuration Chage
    0 0 0 0 0 0 0 0 0
    Experiment
    Ready
    60 60 0 60 60 60 60 60 7
    Planned Config-
    uration Change
    0 0 0 0 0 0 0 0 0
    Unplanned
    Experiment Down
    0 0 60 0 0 0 0 01
    Hall not
    ready reasons
    Target 0 0 0 0 0 0 0 0 0
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 0 0 0 0 0
    Data Ac 0 0 0 0 0 0 0 0 0
    Other 0 0 60 0 0 0 0 0 1

    Comments: 10:00 access: opportunistic since beam going down to check timing cable, takes about 1 hour, do not know when beam becomes available again

    Data Entry by: gilman