    User name strauch

    Log entry time 00:22:50 on December 8,2000

    Entry number 53094

    keyword=Swing shift summary

    Swing shift summary

    16:00 : Still work on air conditioning in the hall. Left arm Q1, Q2, Q3 polarity change, Q2 & Q3 up to 1600 A; Q1,Q2,Q3 to nominal setting p0=3.80860 GeV/c; moved sieve in.
    19:00 : Still work on air conditioning
    20:00 : Hall A ready for sweep.
    21:15 : Beam permit
    21:25 : 50 uA unrastered beam
    21:30 : start 12C run 1704, unrastered beam, sieve
    22:30 : change to 9-foil 12C target
    22:23 : start 9-foil 12C run 1705, unrastered beam, sieve
    23:20 : move out the sieve
    23:25 : start 9-foil 12C run 1706, unrastered beam, open-collimator, 10 uA
    23:30 : start 9-foil 12C run 1707, unrastered beam, open-collimator, 50 uA
    23:40 : change '9-foil' target to 10 cm dummy
    23:55 : start 10 cm dummy target run 1708, unrastered beam, open-collimator, 5 uA
    00:00 : move in sieve