16:00 Start shift with run 1905. Very frequent beam trips, prehaps related to
the fact that Hall B is running at 5.7 GeV?
17:30 Beam goes away for cavity retune.
18:00 No stable beam.
19:00 Beam back, start run 1909, but very frequent trips continue.
19:05 DAQ crash.
19:10 FPP HV trip.
19:15 Start run 1910. Beam seems to hold up now, but the current is not very stable.
20:10 Beam off for injector work to fix Hall B leakage problems.
20:55 Beam is back. Start run 1912.
21:00 Relatively stable beam now.
23:50 Bob Michaels turns on the HV of the rright arm spectrometer from home
to do some tests. This will result in a slight increase of the trigger rate.