Log entry time 16:01:55 on February28,2001
Entry number 57178
keyword=Shift Summary
At start of shift had Hall access for polarity change and investigation of right Q3 He level trips. (False trips from incorrect level readings. Ad Hoc solution is to deliberately overfill)
Spectrometers set for coincidence 15 kinematics
Left:
P0 = 2.638 (Positive polarity) at 29.971 deg
Right:
P0 = 2.291 (Negative polarity) at 35.193 deg.
ep measurement attempted and abandoned by Joe Mitchell due to target failure.
ARC integral measurement implies E = 4236.4 (see Halog entry 57160)
Inspection of BeO shows spot 1mm left and 3mm high (see Halog 57159)
run.........start/stop..........events..........comments
2268......11:46/12:20.......0.5M.......LD2 with 6% radiator
2269......12:26/13:09.......0.5M.......LD2 no radiator
Change to LH2 target.
Observations indicate problems with the H-loop fan. (see Halog 57173)
2270.......13:49/ 14:24.......0.5M........LH2 no radiator
2271.......14.24/15:15........1.0M.........LH2 with 6% radiator
change targets
2272.......15:27/15:28.........just a few.....LD2 with 6% radiator prescales incorrect
2273.......15:30 handed off to swing shift