    Hall A

    3/4/2001 1600-2400
    Experiment #: e94104
    Shift Leader: Gao
    Shift Workers: L.Y. Zhu, J. Arrington

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    1 55 55 30 50 1 25 1 6.58333333333333
    Beam Available
    but Not in Use
    0 5 5 30 10 0 15 0 1.08333333333333
    Beam Not Available
    or Unacceptable
    0 0 0 0 0 0 20 0 0.333333333333333
    Accelerator Con-
    figuration Chage
    0 0 0 0 0 0 0 0 0
    Experiment
    Ready
    1 55 55 30 50 1 45 1 6.91666666666667
    Planned Config-
    uration Change
    0 5 5 30 10 0 15 0 1.08333333333333
    Unplanned
    Experiment Down
    0 0 0 0 0 0 0 00
    Hall not
    ready reasons
    Target 0 0 0 0 0 0 0 0 0
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 0 0 0 0 0
    Data Ac 0 0 0 0 0 0 0 0 0
    Other 0 0 0 0 0 0 0 0 0

    Comments:

    Data Entry by: Gao