Main INDEX
Monthly INDEX
PREV
NEXT
User name Iodice
Log entry time 15:42:08 on March28,2001
Entry number 59476
keyword=Target motion failure AND BeO target check
At 2:45 pm (after about 1 hour of beam down due to injector problems) we had beam back and decided to let Arun do a harp scan for calibrations needed for the arc energy measurements planned for tomorrow. We also took the opportunity to look at the BeO target. Unfortunately the target didn't move.
At about 3:15 (after the settings of the manual heater supply) the IOC has been rebooted. We had still some problems with the read-out of the temperatures.
Called Joe who temporary "fixed" the problem - He needs an access to push a button downstairs.
At 3:30 we were able to see the BeO target which shows the beam in the correct position.