0000 | 0100 | 0200 | 0300 | 0400 | 0500 | 0600 | 0700 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0 | 50 | 55 | 45 | 1 | 15 | 0 | 0 | 3.75 |
Beam Available but Not in Use | 60 | 10 | 5 | 0 | 0 | 45 | 1 | 1 | 4 |
Beam Not Available or Unacceptable | 0 | 0 | 0 | 15 | 0 | 0 | 0 | 0 | 0.25 |
Accelerator Con- figuration Chage | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Experiment Ready | 0 | 1 | 1 | 1 | 1 | 45 | 0 | 0 | 4.75 |
Planned Config- uration Change | 1 | 0 | 0 | 0 | 0 | 15 | 1 | 1 | 3.25 |
Unplanned Experiment Down | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Hall not ready reasons | |||||||||
Target | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSe | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSh | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Data Ac | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Other | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Comments: Finished (e,e'p) and setup for triple run
Data Entry by: Higinbotham