Log entry time 16:04:34 on April16,2001
Entry number 60654
keyword=Day Shift Summary
8:00 - Day shift begins in controlled access.
Cosmic tests were done to ensure the proper function of the spectrometers. There was a problem with the left -HRS Scintillator S1 (SPEC_S1.ADC_L_C4). Things seen to be working now.
There was no beam at all during the day shift; therefore; no data was taken. Hall A remained in controlled access the entire shift. The survey for the spectrometers was done and the magnet polarities were set. Also, the Quads were cycled.