    User name adaq

    Log entry time 11:02:27 on April 26, 2001

    Entry number 61366

    keyword=Beam Time Accounting
    Hall A

    4/25/2001 1600-2400
    Experiment #: commissioning
    Shift Leader: John LeRose
    Shift Workers: Bodo Reitz

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    1 1 0 0 0 0 0 0 2
    Beam Available
    but Not in Use
    0 0 1 .5 0 0 0 0 1.5
    Beam Not Available
    or Unacceptable
    0 0 0 .5 1 1 1 1 4.5
    Accelerator Con-
    figuration Chage
    0 0 0 0 0 0 0 0 0
    Experiment
    Ready
    1 1 1 1 1 1 1 1 8
    Planned Config-
    uration Change
    0 0 0 0 0 0 0 0 0
    Unplanned
    Experiment Down
    0 0 0 0 0 0 0 00
    Hall not
    ready reasons
    Target 0 0 0 0 0 0 0 0 0
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 0 0 0 0 0
    Data Ac 0 0 0 0 0 0 0 0 0
    Other 0 0 0 0 0 0 0 0 0

    Comments: 16:00 to 18:00 spent on ep beam energy measurement 18:00 to 19:30 beam used by accelerator for accelerator studies 19:30 beginning of shutdown for Hall A

    Data Entry by: J. LeRose