Here is a summary of polarized 3He target related work done on the 06/11 maintanance day:
1) Target alignment/survey; target was shifted closer to (0,0) in beam coordinates.
2) Laser profile checked
3) Replaced and adjusted the EPR photodiode.
4) Added a needle valve for He3 gas line.
5) Installed cooling for lasers in the laser hut.
6) Replaced the laser hut air-conditioner.
7) Cross-hairs on the BeO foil re-drawn