• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name Nilanga

    Log entry time 02:18:48 on June13,2001

    Entry number 62935

    keyword=Summary of target activities during the maintanance data

    Here is a summary of polarized 3He target related work done on the 06/11 maintanance day:

    1) Target alignment/survey; target was shifted closer to (0,0) in beam coordinates.
    2) Laser profile checked
    3) Replaced and adjusted the EPR photodiode.
    4) Added a needle valve for He3 gas line.
    5) Installed cooling for lasers in the laser hut.
    6) Replaced the laser hut air-conditioner.
    7) Cross-hairs on the BeO foil re-drawn