0:00 Take data in Longitudinal polarization at 0 degrees beam half-wave plate IN and target half-wave plate OUT. Beam current: 12 muA.
1:02 Called MCC to move beam half-waveplate OUT.
2:45 NMR measurement. Polarization: 37 %
6:00 Parity DAQ failed to start. Runs 1934/20934 are junk! Coda killed and rebooted. Coda for the right arm failed to start. Runs 1935/20935 are also junk. Coda killed again and reset.
6:35 Taking data again.
6:50 EPR measurement. Laser # 4 and # 7 off. During runs 1936/20936.
7:02 EPR done. Polarization: 38.8 %
8:00 Hand shift over to Day crew.
Run Summary:
******************
(i/o)
1928/20928 23:58 - 0:59 Production Run. 527 (T1); 616 (T3)
(o/o)
1929/20929 1:05 - 1:36 Production Run. 350 (T1); 380 (T3). Stopped early to change HV for PRL1. HV increased by 300 V to - 1793.
1930/20930 1:38 - 2:45 Production Run. 695 (T1); 787 (T3)
1931/20931 2:54 - 3:55 Production Run. 527 (T1); 641 (T3)
1932/20932 3:56 - 4:58 Production Run. 563 (T1); 653 (T3)
1933/20933 4:59 - 5:59 Production Run. 595 (T1); 710 (T3) The helicity for the left arm was strange possibly due to the coda problems. The electron events may not be trustworthy.
1936/20936 6:33 - 7:34 Production Run. 639 (T1); 726 (T3) EPR measurement during runs.
1937/20937 7:35 - ?? Production Run.