    Log entry time 16:04:58 on July 19, 2001

    Entry number 66748

    keyword=Beam Time Accounting
    Hall A

    7/19/2001 0800-1600
    Experiment #: e99117
    Shift Leader: gilman
    Shift Workers: roedelbronn, savvinov

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    27 50 38 5 43 55 15 0 3.88333333333333
    Beam Available
    but Not in Use
    0 0 7 0 0 0 0 0 0.116666666666667
    Beam Not Available
    or Unacceptable
    33 10 15 55 17 5 0 0 2.25
    Accelerator Con-
    figuration Chage
    0 0 0 0 0 0 45 1 1.75
    Experiment
    Ready
    60 60 60 60 60 60 60 60 8
    Planned Config-
    uration Change
    0 0 0 0 0 0 0 0 0
    Unplanned
    Experiment Down
    0 0 0 0 0 0 0 00
    Hall not
    ready reasons
    Target 0 0 0 0 0 0 0 0 0
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 0 0 0 0 0
    Data Ac 0 0 0 0 0 0 0 0 0
    Other 0 0 0 0 0 0 0 0 0

    Comments: 10:30 rebooting Compton DAQ 14:20 Hall A in Controlled Access. Anticipated down time 1.5 - 2 hours.

    Data Entry by: gilman