    Log entry time 08:01:33 on July 24, 2001

    Entry number 67367

    keyword=Beam Time Accounting
    Hall A

    7/24/2001 0000-0800
    Experiment #: e99117
    Shift Leader: Seonho Choi
    Shift Workers: Kevin Kramer, Lisa Kaufman

    00000100020003000400050006000700Total Time
    Acceptable Beam
    in Use
    42.5 36.6 46.6 32.3 40.9 49.4 15 51.0 5.23833333333333
    Beam Available
    but Not in Use
    15 0 0 23 0 0 45 0 1.38333333333333
    Beam Not Available
    or Unacceptable
    2.5 23.4 13.4 4.7 19.1 10.6 0 9.0 1.37833333333333
    Accelerator Con-
    figuration Chage
    0 0 0 0 0 0 0 0 0
    Experiment
    Ready
    45 60 60 37 60 60 15 60 6.61666666666667
    Planned Config-
    uration Change
    15 0 0 0 0 0 45 0 1
    Unplanned
    Experiment Down
    0 0 0 23 0 0 0 00.383333333333333
    Hall not
    ready reasons
    Target 15 0 0 0 0 0 45 0 1
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 0 0 0 0 0
    Data Ac 0 0 0 23 0 0 0 0 0.383333333333333
    Other 0 0 0 0 0 0 0 0 0

    Comments: 00:45 Stopped Run 2218 for target polarizationmeasurement 01:00 Start new run 2219/21219/1365 01:15 Cavity problem, beam down 01:30 Beam back 01:30 Beam position is a little off, asked MCC for minor adjustment 03:00 Failure to end Left spectrometer run. Reboot ROC14 and ROC2. 03:20 Left spectrometer DAQ is working. 04:05 Noticeable path length drift, beam off to fix problem 04:20 Beam back on 06:00 Finished taking data at 180 degrees. Took NMR and EPR measurements and rotated target to 270 degrees to begin taking data.

    Data Entry by: Seonho Choi