    User name adaq

    Log entry time 16:12:10 on August 21, 2001

    Entry number 71705

    keyword=Beam Time Accounting
    Hall A

    8/21/2001 0800-1600
    Experiment #: e97103
    Shift Leader: D.W.Higinbotham
    Shift Workers: O.Hansen, P.Zolnierczuk

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    58 55 0 0 0 0 0 0 1.88333333333333
    Beam Available
    but Not in Use
    2 5 0 0 0 0 0 0 0.116666666666667
    Beam Not Available
    or Unacceptable
    0 0 0 0 0 0 0 0 0
    Accelerator Con-
    figuration Chage
    0 0 1 1 1 1 1 1 6
    Experiment
    Ready
    1 1 1 1 1 1 20 0 6.33333333333333
    Planned Config-
    uration Change
    0 0 0 0 0 0 0 0 0
    Unplanned
    Experiment Down
    0 0 0 0 0 0 40 11.66666666666667
    Hall not
    ready reasons
    Target 0 0 0 0 0 0 0 0 0
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 0 0 0 0 0
    Data Ac 0 0 0 0 0 0 0 0 0
    Other 0 0 0 0 0 0 0 0 0

    Comments: Around 2pm today the Hall A magnets tripped off. As of 16:00 all magnets except D right had been restored. D right was still ramping.

    Data Entry by: Higinbotham