• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name S. Sirca

    Log entry time 15:55:30 on August26,2001

    Entry number 72575

    keyword=Summary of day shift


    As of 08:00, switching to kinematics #4 is in progress. Waiting for beam.

    Run# Start/Stop Comments, events Left/Right/Total (cumulative)
    -------------------------------------------------------------------------------
    09:04 Left at +2.630 GeV/c, Right at -2.630 GeV/c ready
    10:00 Stuck-slit problem in the injector fixed
    13:00 CW beam ready for delivery
    3147/31147 13:40 Run for harp scan (harp run #1392)
    13:40/14:50 Redoing the beam optics
    14:30 Target polarisation: 45.3 % (NMR) 45.1% (EPR)
    14:50 Harp run #1393: beam spreads are still around 70 um
    16:00 Waiting for MCC to make beam spreads > 100 um
    -------------------------------------------------------------------------------